Health
facility planning services to the NHS, major construction
contractors and consultancy practices |
|
| Private
Finance Initiative (PFI). We have been involved in PFI since
its introduction in 1995, as the primary procurement method
for major health service assets. Typically, we are invited into
a consortium drawn together by a major construction contractor
or consultancy practice to help compile a bid for a project
in the UK. Current active project work . . . |
Birmingham New Hospitals PFI
Project stage reached to date: Preferred Bidder
Approximate project construction cost: £335 million
Central Manchester PFI
Project stage reached to date: Preferred Bidder
Approximate project construction cost: £190 million
Lewisham PFI
Project stage reached to date: Preferred Bidder
Approximate project construction cost: £47 million
Hull Haematology & Oncology
Project stage reached to date: ITN
Approximate project construction cost: £20 million
Northern General Hospitals Trust PFI
Project stage reached to date: Preferred Bidder
Approximate project construction cost: £24 million
South London and Maudsley P21
Project stage reached to date: Preferred Bidder
Approximate project construction cost: £TBA
Birmingham Ambulatory Care Centre PFI
Project stage reached to date: Construction
Approximate project construction cost: £40 million
|
|
|
|