Health
facility planning services to the NHS, major construction
contractors and consultancy practices |
|
| First
Wave PFI projects ... During the First Wave of PFI, we assisted
our consortia to achieve Preferred Bidder stage on six projects,
which represented a success rate of 55%. Subsequently, some
of the bidders that had reached Preferred Bidder stage were
stood-down by the major acute scheme prioritisation in June
'97 or due to affordability issues. |
Gloucestershire Royal Infirmary, Gloucester PFI
Project stage reached to date: Preferred Bidder stood-down
Approximate project construction cost: £72 million
Stone Grove Development, Sheffield PFI
Project stage reached to date: Preferred Bidder stood-down
Approximate project construction cost: £30 million
Leicestershire Mental Health Unit, Leicester
Project stage reached to date: Preferred Bidder stood-down
Approximate project construction cost: £8 million
Castle Hill Phase 4, Hull
Project stage reached to date: Preferred Bidder stood-down
Approximate project construction cost: £6 million
|
|
|
|